New-build

Domed roof coal-fired power plan, Hamburg (DE)

Client
Holzbau Amann GmbH
Albtalstrasse 1, DE-79809 Weilheim-Bannholz, Germany

Developer
Vattenfall Europe Generation AG & CO. KG
Vom-Stein-Strasse 39, DE-03050 Cottbus, Germany

Year of construction
2010-2011

Planning contract
• Structural development
• Structural analysis for approval
• Structural analysis

Project description
The domed structures of the Hamburg-Moorburg coal-fired power plant have a span of 115 m and were erected with cantilever construction methods despite the low overall height of less than one metre. They have a capacity of up to 170,000 tons with a dumping height of up to 60 m. The design was particularly challenging due to the enormous deformations caused by the asymmetrical filling levels.

• Dome constructions as glued laminated timber
• Two domes with a diameter of 115 m
• One dome with a diameter of 70 m
• Total covered area: 24,000 m²
• Assembly of the dome construction with cantilever construction methods